Case Study

Litchardon Cross Solar Energy Park


  • Barnstaple, Devon
  • 49.9

Project scope

Solutions implemented


The Work Scope by UPL included the overall responsibility for the Commissioning and Energisation elements of the Project. We undertook the Commissioning and Energisation of the NGED Compound Substation & Control Room, and the Client Customer Substation. We were also responsible for the ongoing Safety from the System.

Contact our team

Delivered

Our services

The Litchardon Cross Solar Energy Park is located in Barnstaple, Devon. Our services included:

  • NGED 132kV Point of Connection (POC) Compound Substation and Control Room
  • Client 132/33kV Customer Substation

Summary

Key Facts


  • Commissioning & Energisation of the 132kV / 33kV Substations and Control Room

  • Full Collaboration & Communication with Client and Solar EPC Contractor

  • On Time Energisation of the DNO Substation and Control Room

  • Diligent Safety Management with No Accidents or Incidents