Case Study

Doverdale Solar Farm


  • Wychavon, Worcestershire
  • 50

Project scope

Solutions implemented


The Work Scope by UPL involved HV Cable Terminations, installation of Cable Support Frames, and Trefoil arrangement to maintain separation and Mechanical integrity.

We undertook the Commissioning of 10 x BESS MVPS Inverter Stations, Jointing of 33kV Terminations of 10 x BESS MVPS Inverter Stations & Customer Substation. AC Installation of 10 x BESS MVPS Inverter Stations.

Contact our team

Delivered

Our services

The Doverdale Solar Farm is located in Wychavon, Worcestershire. Our services included:

  • Fibre Termination & SCADA Works
  • HV Cable Terminations and dressing within the Substation / Cable Route interface
  • Installation of Cable Support Frames to provide secure Mechanical support and maintain clearances
  • Trefoiling and Cleating of Cables to manage Electromagnetic forces and ensure a tidy installation

Summary

Key Facts


  • Commissioning of BESS MVPS Inverter Stations

  • Full Collaboration & Communication with Client and Solar EPC Contractor

  • Enabled downstream Testing / Commissioning to proceed with a clear and accessible installation

  • Diligent Safety Management with No Accidents or Incidents